CABLE PLOUGHING - STRENGLÖGN - Vatnshamrar að Ferjubakka - Vesturland
Description du marché
There are two work sections involved, namely cable laying from Vatnshamrar to Hvítá and from Ferjubakki to Hvítá. The cable installation is a pure transmission line, and therefore no ground-mounted substations are required along the route. The high-voltage cables consist of 3 units of 1x300 mm², 36 kV over approximately 6.3 km, and 3 units of 1x240 mm², 36 kV over approximately 6.3 km. In total, 6 cables are to be ploughed in parallel along a section of approximately 6.3 km. It is requested that fiber optic ducts be installed in parallel with the works on behalf of RARIK. It is assumed that the project will commence on June 22 and be completed by August 17, 2026.